UK taxpayers on the hook for US$1.3 billion because of wasted wind power

Despite record wind generation, the grid can’t handle the influx, forcing operators to pay wind farms to shut down

Reading Time:2 minutes
Why you can trust SCMP
1
A wind farm near Great Wilbraham, Britain. Photo: EPA-EFE

It’s set to be a record year for wind power in the UK, at least in terms of how much goes to waste.

Advertisement

Burgeoning capacity and blustery weather should have driven huge growth in output in 2024. But the grid can’t cope, forcing the operator to pay wind farms to turn off, a cost ultimately borne by consumers. It’s a situation that puts at risk plans to decarbonise the network by 2030 and makes it harder to cut bills.

Crucial to the net-zero grid target is a massive buildout of renewable power, particularly from wind. Britain has boosted its offshore fleet by 50 per cent in the past five years and is set to double it in the next five, BloombergNEF data show.

But the grid hasn’t expanded at the same pace. As a result, the operator is increasingly paying wind farms, particularly those in Scotland, not to run. So far this year, the UK has spent more than £1 billion (US$1.3 billion) in “congestion costs” to turn off plants that can’t deliver electricity because of grid constraints, and switch on others.

Last month, for example, when Storm Bert swept across the UK, some of its newest and biggest wind parks were still. Scotland’s US$3.8 billion Seagreen project, owned by SSE Plc and TotalEnergies SE, was shut off. SSE’s Viking development on the Shetland Islands was also closed.

Advertisement

The utility aims to build an even bigger wind farm off Scotland that could further aggravate the bottleneck unless the grid is expanded. In a statement, it said developers need to harness Scottish renewables to deliver on the UK’s energy-security targets. And to that end, transmission infrastructure is key.