Advertisement

MTR Corp should pay part of railway delay cost, experts say

The MTR Corporation should pay part of the HK$4.62 billion in extra costs that the delayed cross-border high-speed rail link is expected to incur, experts in transport and engineering say.

Reading Time:2 minutes
Why you can trust SCMP
Construction on the express link's West Kowloon terminus. Photo: Felix Wong

The MTR Corporation should pay part of the HK$4.62 billion in extra costs that the delayed cross-border high-speed rail link is expected to incur, experts in transport and engineering say.

Advertisement

It was likely the bill would be split between the government, MTR Corp and contractors as the railway giant was responsible for some parts of the two-year delay in the project, veteran transport analyst Dr Hung Wing-tat and engineer Dr Greg Wong Chak-yan both said yesterday.

The MTR Corp could claim against its contractors if they were found at fault, Hung, of Polytechnic University, also said.

Advertisement

On Monday, the company released its latest estimate of the project cost - HK$71.52 billion, 6.9 per cent more than the HK$66.9 billion the Legislative Council approved in January 2010. It said the new figure was based on "a detailed review of the revised programme" that would now see the link finished in 2017.

Hung and Wong said given the scant details, they could not tell if the figure was reasonable.

Advertisement
Advertisement