Opinion | Hong Kong must cut the red tape and start churning out public housing to tackle the acute shortage of homes
- At the crux of delays is a lack of transparency. An official one-stop platform disclosing the progress of each public housing project would allow government bureaus to be held accountable, and development timelines to be better respected
02:08
To add to the complexity of the problem, many public housing sites face hurdles before they can get to the “spade ready” point. Three such cases were scrutinised in the report. They illustrate how housing projects often do not proceed smoothly beyond the stage of rezoning, due to delays in procedures, including facility and land clearance, land resumption and engineering studies.
The first case is a site at the junction of Sung Wong Toi Road and To Kwa Wan Road in Ma Tau Kok. The original site plan was for 600 public housing units. This was later replaced by a plan for 100 units of transitional housing, after a small part of the site was not vacated on time.
The facility, used as an animal management centre by another government department, could only be moved out in 2023 due to a shortage of nearby relocation options. The site’s meandering timeline highlighted a seeming lack of coordination and common mandate among government departments on the land clearance schedule.